On February 4, 2017, the Zhenxing Cement Second Line raw material roller press system was officially put into operation. From now on, our company will dispatch 8 professional and skilled construction personnel to carry out follow-up transportation maintenance of the raw meal system to ensure the normal operation of the raw meal mill system.
Since the start of construction of the project, all employees involved in the construction have resisted the severe cold and worked overtime with the guarantee of construction safety, the premise of construction quality, and the purpose of high and excellent service. After 22 days and nights of intensive construction, they have overcome all construction difficulties and completed the arduous task of interfacing the roller press system of the raw meal mill workshop with the original raw meal system within the construction period limited by the owner and the general contractor. So far, the raw meal mill system is operating well.