On the morning of June 15, the potassium-calcium-silicon-magnesium fertilizer production line project of Inner Mongolia Sinoma Dingyuan Fertilizer Co., Ltd. achieved 6.15 stand-alone commissioning as planned. The mechanical and electrical equipment installation contract for this project was signed in October 2016, with a three-month winter break. Our company is responsible for all electromechanical equipment such as raw material system, raw material system, firing system, cooling system, grinding system, packaging system, non-standard installation tasks, as well as the production and installation tasks of kiln tail preheater and tower steel structure of the project.
![]()