? ? ? ?The Changshan project in Zhejiang was built by Changshan Nanfang Cement Co., Ltd. and was contracted by Tianjin Cement Industry Design and Research Institute Ltd. Project. Our company is responsible for the mechanical and electrical equipment installation of the raw material grinding roller press technical transformation project and the cement grinding project.
Due to the late determination of the contract, the installation cycle of the entire raw meal transformation system is only two months. It is necessary to complete the non-standard manufacturing and installation of nearly 1000 tons of steel structures and the installation of 1000 tons of process equipment, as well as all supporting works such as corresponding electrical, piping, and thermal insulation. At the beginning of the project, we caught up with continuous heavy rains and construction in midsummer, which was extremely hot and scorching heat. The project department dispatched elite soldiers and invested more than 140 people in a short period of time, ensuring that all pre-installation tasks were completed before the interface kiln was stopped, and winning the general contractor and The owner spoke highly of it. The project is expected to be put into operation in early September.