? ? ? ?The Changshan project in Zhejiang was built by Changshan Nanfang Cement Co., Ltd. and was contracted by Tianjin Cement Industry Design and Research Institute Ltd. Project. Our company is responsible for the mechanical and electrical equipment installation of the raw material grinding roller press technical transformation project and the cement grinding project.
The technical transformation project of the raw material grinding system of Changshan Nanfang Cement Co., Ltd. started production on May 26, when the first batch of steel entered the site. By September 5, the steel structure, equipment, electrical, non-standard parts, and pipelines were all installed. More than 140 people were not afraid of hard work and persisted in working in the hot summer. It took 102 days for the raw material grinding system to be successfully put into production.