? ? ? ?The kiln tail flue gas SCR denitrification renovation project of Huaxin (Daye) Co., Ltd., with the high attention of the company's leaders and the close cooperation of the project department management team and all construction personnel on site, started on-site from July 25, 2023 to October 18. After 86 days of successful ignition, the owner completed the demolition of the humidification tower and air pipe (about 154 tons). It has also manufactured and installed reactor shells, brackets, non-standard reactor import and export, steel structure fabrication and installation (about 350 tons), equipment installation (about 180 tons), electrical installation, etc., which have been unanimously praised by the owner and general contractor. It is also the only denitrification transformation project in Sinoma's overseas denitrification project that is completed ahead of schedule within the contract period.
?
?
?
Contribution by Su Zhoujun